How long does an RTLS deployment take from first meeting to live operation?

There is no generally honest answer to the timeline question, because an RTLS project is not a boxed product but process, radio physics and integration at once. The phases, however, are well defined - and so are the places where timelines slip.

The phases

  1. Fixing the goal and use case: why positioning is needed, what counts as accuracy, what success means.
  2. Site survey: radio behaves in the specific building; brochure figures gain real meaning here.
  3. PoC / pilot: in one representative zone we measure whether the chosen technology meets the target.
  4. Dimensioning and proposal: pilot results produce the infrastructure sizing and the concrete cost.
  5. Installation and integration: after the hardware, the real work is often the data link - API, ERP/WMS, corporate systems.
  6. Acceptance and operation: training, maintenance and replacement routines, tracking metrics in operation.

What usually slips

The most common source of delay is not the radio but the organization: goal uncertainty, IT and security approval cycles, the availability of corporate systems, and procurement lead times for devices (tags, anchors, gateways). Technology selection can be decided relatively quickly; integration and internal approvals supply the months.

Where real numbers come from

If the pilot is narrowed to a single well-defined zone and one measurable goal, it is substantially shorter than the full deployment, whose length is driven by integration depth and internal processes. Concrete durations come from the survey and pilot results - until then every number is an assumption. Anyone promising immediate days without pilot and survey is selling marketing instead of an estimate.

How to start

With a single, well-bounded use case and measurable success criteria. Such a pilot is cheaper and faster, and it grounds every further estimate - including the question of how long a 10,000 m2 hall takes to cover.